Customer: Boral Cement Works, Berrima NSW
Project type: Electrical Construction
Project duration: 3 weeks
Touchstone Systems was engaged to deliver the electrical installation works for a new Liquid Resistance Starter (LRS) for the Coal Mill 6.6kV motor.
The scope included the decommissioning and removal of the existing LRS unit and associated control cabinets, followed by installation of the new LRS system. All works were completed during the site’s annual shutdown to support timely plant restart.
Key deliverables included:
Due to site access constraints, the installation required careful planning and execution, including the use of a crane and controlled manual positioning of the unit. Touchstone Systems worked closely with site engineers to ensure the LRS was commissioned and operational in line with the shutdown schedule.