Customer: GM3 Appin Mine, Douglas Park, NSW
Project type: Engineering and Construction
Project duration: 4 months
Touchstone Systems was engaged to deliver the full electrical construction and engineering package for the installation of a new Compressor House at the Appin Vent Shaft 6 (VS6) facility in Douglas Park. The project involved the careful cutover of four existing compressors into the new structure, with works staged to ensure operational vent shaft pressures were maintained throughout the transition.
The scope encompassed all electrical infrastructure within the new Compressor House, from cable tray and power distribution through to compressor integration, fire detection, and safety compliance—delivered within a tightly managed cutover program coordinated with GM-3’s operational requirements.
Key deliverables included:
The project required close coordination with GM-3 to manage access, isolations, and compressor cutover sequencing without disrupting site operations. Touchstone Systems delivered the complete electrical scope on time, ensuring the new Compressor House met all operational, safety, and regulatory requirements.